Code 01CFAC5012
Project Area / Project Category Area 1 / Community Facilities
Location Nowra
Description Nowra Integrated Youth Services Centre (Cnr Kinghorne & Plunkett Streets)
Strategy To provide a facility for a variety of youth activities for the community of Nowra and immediately surrounding communities.
Project Estimate Remaining cost of $122,185.29 at July 2018
Indexed Estimate $154,019.52
Apportionment Recoupment of cost apportioned to future development is 100%.
Nexus The population accommodated in Planning Area 1 by both existing and future development up to 2036 will generate the demand for this project. The contribution rate calculation therefore reflects this planning philosophy. When this project was created in May 2004, the apportionment to development was 21.62%. The recoupment of the remaining cost owed by development is now apportioned at 100%.
Supporting Information

Supporting Information can be viewed here.

Land Acquisition Estimate $600,000.00 at May 2004
Timing The project has been completed.

Contribution Rate

Financial Year Contribution Rate Type Contribution Rate Existing ET / M2 / SP Future ET / M2 / SP Total ET / M2 / SP
2020 Equivalent Tenement $29.98 20636 5137 25773