Code | 03ROAD2023 |
Project Area / Project Category | Area 3 / Roads and Traffic |
Location | St Georges Basin |
Description | St. Georges Basin Village access road and traffic facilities |
Strategy | To provide a new access road and traffic facilities to facilitate development of the St Georges Basin Village Centre. |
Project Estimate | $2,466,593.00 in Jun 2009 |
Indexed Estimate | $3,770,541.40 |
Apportionment | The apportionment to future development is 100%. |
Nexus | The project is a critical part of the local road network and necessary to enable land zoned B4 Mixed Use to the east of Island Point Road to be developed. |
Supporting Information | The project is described in Shoalhaven DCP 2014 Chapter N23 St Georges Basin Village Centre. |
Land Acquisition Estimate | $293,293.00 in Jun 2009 |
Timing | Development dependent. |