Code 05ROAD2001
Project Area / Project Category Area 5 / Roads and Traffic
Location Mollymook
Description Bishop Drive (Matron Porter Drive to Princes Highway)
Strategy To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand.
Project Estimate $9,850,625.00 in Nov 2005
Indexed Estimate $14,959,636.34
Apportionment The apportionment to future development is 33.3%.
Nexus The project is critical for ensuring that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development.
Supporting Information

Supporting information can be found here.

Land Acquisition Estimate $4,400,000.00 in Nov 2005
Timing Development dependent.

Contribution Rate

Financial Year Contribution Area Contribution Rate Type Contribution Rate Existing ET / M2 / SP Future ET / M2 / SP Total ET / M2 / SP
2019 1 Equivalent Tenement $5,426.05 1082 259 1341
2019 2 Equivalent Tenement $1,808.69 809 33 842
2019 3 Equivalent Tenement $18,086.85 99 152 251
2019 4 Equivalent Tenement $12,660.79 67 61 128