Code 04ROAD2003
Project Area / Project Category Area 4 / Roads and Traffic
Location Sussex Inlet
Description Medlyn Avenue upgrade (For 750m from The Springs Road), Sussex Inlet
Strategy To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand.
Project Estimate $123,980.00 in Nov 2009
Indexed Estimate $154,253.08
Apportionment Recoupment of cost apportioned to future development is 26.2%.
Nexus The project ensures that new development pays an equitable apportionment of costs associated with providing suitable community facilities which directly services demand created by development.
Supporting Information

Supporting information can be found here.

Land Acquisition Estimate $0.00
Timing Not Applicable. The project has been completed.

Contribution Rate

Financial Year Contribution Rate Type Contribution Rate Existing ET / M2 / SP Future ET / M2 / SP Total ET / M2 / SP
2019 Equivalent Tenement $3,672.69 31 11 42