| Code | 04CFAC0003 |
| Project Area / Project Category | Area 4 / Community Facilities |
| Location | Various |
| Description | Planning Area 4 - Community facility upgrades (various locations) |
| Strategy | To provide community facilities to meet anticipated demand from development. |
| Project Estimate | $600,000.00 in May 2018 |
| Indexed Estimate | $619,956.00 |
| Apportionment | The apportionment to future development is 21.12%. |
| Nexus | The population accommodated in Planning Area 1 in both existing and future development up to 2026 will generate the demand for this project. The contribution rate calculation therefore reflects this planning philosophy. |
| Supporting Information | |
| Land Acquisition Estimate | $0.00 |
| Timing | Development dependent. |