| Code |
03ROAD2019 |
| Project Area / Project Category |
Area 3 / Roads and Traffic |
| Location |
St Georges Basin |
| Description |
Tasman Park Estate gravel upgrade (The Wool Rd, The Basin Road & Island Point Rd) |
| Strategy |
To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand. |
| Project Estimate |
$89,591.00 in Dec 2009 |
| Indexed Estimate |
$136,461.48 |
| Apportionment |
Recoupment of cost apportioned to future development is 100%. |
| Nexus |
The project ensures that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development. |
| Supporting Information |
Supporting information can be found here. |
| Land Acquisition Estimate |
$0.00 |
| Timing |
Not Applicable. The project has been completed. |