| Code |
01ROAD3007 |
| Project Area / Project Category |
Area 1 / Roads and Traffic |
| Location |
Berry |
| Description |
Beach & Tannery Road upgrade |
| Strategy |
To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand. |
| Project Estimate |
$1,598,000.00 in July 2018 |
| Indexed Estimate |
$1,618,774.00 |
| Apportionment |
The apportionment to future development is 38.53%. |
| Nexus |
The project is critical for ensuring that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development. The demand for this project includes 31.60% assumed through traffic which equates to $271,228 in Nov 2005 and is apportioned to Council. Contribution Area 1 is a rural residential area and is therefore apportioned 100% to development. |
| Supporting Information |
Supporting Information can be viewed here
|
| Land Acquisition Estimate |
$0.00 |
| Timing |
2020/25 |