Code 01ROAD2133
Project Area / Project Category Area 1 / Roads and Traffic
Location Berry
Description Beach and Tannery Road upgrade (road and bridge) related to quarry works
Strategy To maintain safe public road networks associated with quarry works.
Project Estimate $284,167.00 in Sep 2008
Apportionment The apportionment to future development is 100%.
Nexus The project is to ensure that quarry transport pays an equitable apportionment of costs associated with maintaining a suitable road network. The maintenance rate is as per the rate established in Amendment 71 of Council's 1993 Contributions Plan.
Supporting Information

Supporting Information can be viewed here

Land Acquisition Estimate $0.00
Timing Ongoing.

Contribution Rate

Financial Year Contribution Rate Type Contribution Rate Existing ET / M2 / SP Future ET / M2 / SP Total ET / M2 / SP
2018 Tonne $0.39