Code 01ROAD0150
Project Area / Project Category Area 1 / Roads and Traffic
Description Roundabouts - Yalwal Road/Rannoch Drive and Yalwal Road/Lightwood Drive
Strategy To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand.
Project Estimate $1,103,760.00 in Sep 2013
Indexed Estimate $1,203,323.06
Apportionment The apportionment to future development is 62.45%.
Nexus The project is critical for ensuring that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development.
Supporting Information

Supporting Information can be viewed here

Land Acquisition Estimate $0.00
Timing Development dependent.

Contribution Rate

Financial Year Contribution Rate Type Contribution Rate Existing ET / M2 / SP Future ET / M2 / SP Total ET / M2 / SP
2018 Equivalent Tenement $937.84 791 791