| Code |
01CFAC2012 |
| Project Area / Project Category |
Area 1 / Community Facilities |
| Location |
Nowra |
| Description |
Nowra Integrated Youth Services Centre (Cnr Kinghorne & Plunkett Streets) |
| Strategy |
To provide a facility for a variety of youth activities for the community of Nowra and immediately surrounding communities. |
| Project Estimate |
$175,903.97 in Mar 2010 |
| Indexed Estimate |
$218,870.78 |
| Apportionment |
Recoupment of cost apportioned to future development is 100%. |
| Nexus |
The population accommodated in Planning Area 1 in both existing and future development up to 2026 will generate the demand for this project. The contribution rate calculation therefore reflects this planning philosophy. When this project was opened in May 2004 the apportionment to development was 21.62%. The recoupment of the remaining cost owed by development is apportioned to 100%. |
| Supporting Information |
Supporting Information can be viewed here |
| Land Acquisition Estimate |
$600,000.00 in May 2004 |
| Timing |
The project has been completed. |